Why does a four-lane parkway, built for a community designed down to its color palette, squeeze into two lanes over one desert wash?
Anyone who drives Thompson Peak Parkway past Desert Camp knows the spot. Between E. Desert Camp Drive and E. Windgate Pass Drive, the road crosses the Reata Wash, and four travel lanes merge into two to cross a single bridge. The bike lanes narrow with them. The narrowing is half of a plan that has sat unfinished for about 26 years, and on Monday, Nov. 2, the City of Scottsdale starts building the other half.
A bridge designed in pairs and built alone
When DC Ranch was being developed, the city and the developer agreed that the developer would design two bridges over the Reata Wash but build only one. According to the city's project page, traffic in the new community was too light to justify the second. DC Ranch built its bridge in 2000 as a half-street improvement. The original design assumed the city would add the matching structure later, which, as city staff put it, "did not come to fruition."
The agreement put the trigger on traffic volume. Once volume warranted it, the city was obligated to build the second bridge. In the end, cars weren't what forced the issue. The city says the existing bridge has kept up with vehicle traffic as the area developed. Bicycles changed the math. More cyclists on this stretch made the merge a safety concern for drivers and riders alike.
So a bridge the founding agreement linked to traffic counts is being built for a reason it never mentioned.
| When | What happened |
|---|---|
| 2000 | DC Ranch builds the existing bridge as a half-street improvement |
| 2019 | Voters approve bond Question 2, which includes Project 62, the Reata Pass Wash bridge |
| Aug. 7, 2025 | City staff present the design to the Paths & Trails Subcommittee at 30 percent completion |
| Sept. 22, 2026 | City Council approves the construction contract on its consent agenda |
| Nov. 2, 2026 | Construction begins |
| About 12 months later | Expected completion, per the city |
What the bridge costs now, against what voters saw
The bridge now costs more than the figure on the 2019 ballot. Three numbers lay out the gap, and each one measures something different:
- $6.3 million is what the 2019 bond package listed for the bridge when voters approved it, as reported by Scottsdale Progress.
- $8,085,461.26 is the ceiling on the construction contract with Ames Construction, the low bidder, which City Council approved on consent on Sept. 22, 2026.
- $14.2 million is the total project budget the city lists, funded by the 2019 bond with the rest coming from Scottsdale's 0.2% transportation sales tax.
The second and third figures don't conflict. One is the contract to build the bridge, and the other is the whole project budget. The useful comparison is the first two. The construction contract alone came in about $1.8 million above what the bond package listed for the entire bridge. Scottsdale Progress put the project among the 2019 bond items running "far north of the original estimate." The paper also counted 26 bond projects listed as completed, leaving the city "still less than half way to the bond finish line."
The contract includes more than a deck and railings. According to the city staff report Scottsdale Progress quoted, it covers a public art component and minor improvements to the existing bridge.
What the first phase looks like from the road
For now, the work happens mostly out of sight. The city says construction runs Monday through Friday from 7 a.m. to 5 p.m. The first phase includes:
- Salvaging and relocating native plants, with a temporary plant nursery on site
- Locating underground utilities and moving them if needed
- Drilling shafts for the bridge supports
Much of this happens below grade in the Reata Wash. The contractor's staging area also sits on site, and the city says travel lanes won't be affected during this phase.
The start date has already moved once. DC Ranch's October 2026 Ranch Roundup expected work to begin Oct. 26. The city's project page, last updated Oct. 16, says Nov. 2. The city hasn't published lane plans for the phases after drilling, so the city page is the place to watch once the supports are in.
What changes when both halves exist
The 2025 design presentation shows how closely the new bridge copies the old one. It calls for two 12-foot travel lanes, a five-foot bike lane, and a five-foot sidewalk, with a separation barrier between the sidewalk and traffic. Its configuration and look match the existing bridge. City staff told the subcommittee the two structures would differ but share aesthetic features.
Once it's finished, each bridge carries one direction of traffic, and the existing structure stops handling both. The city says this completes Thompson Peak Parkway as a continuous four-lane road with bike lanes from Scottsdale Road to 100th Street. That's the road's planned final shape, which the city calls its "ultimate cross-section," and it improves access to nearby parks. The design goals also listed multiuse and trail-network connections, plus coordination with DC Ranch on where the bridge meets local paths and trails.
The 2000 bridge changes too. According to the Ranch Roundup, its wood railing will be replaced with a metal railing that matches the new bridge, which should mean less maintenance on both structures. The city expects the full job to take about 12 months.
The wash gets a second project, on a slower clock
The bridge isn't the only city project on the Reata Wash. Scottsdale's Reata Wash Flood Control Study covers a broad floodplain running roughly from Pinnacle Peak Road to the Central Arizona Project Canal, and it lists Thompson Peak Parkway among the arterials in that area. The bridge took 26 years to arrive. The flood control effort is on its own long timeline. DC Ranch's most recent project update, from June 2026, said the city was waiting for FEMA to approve a Conditional Letter of Map Revision. Construction plans would come after that approval, and construction funding wasn't in the city's capital improvement plan for at least the next several years. For now, the bridge is the Reata Wash project with a start date.
The week the drills arrive
The bridge work starts during a full week on the DC Ranch calendar. Desert Camp Community Center at 9260 E. Desert Camp Dr. is right by the Desert Camp Drive end of the bridge.
- Friday, Oct. 30: Comedy Night at The Homestead, 18600 N. 98th St., 6:30 to 8 p.m., ages 21 and over, $23. Doors open at 6 p.m.
- Saturday, Oct. 31: The McDowell Sonoran Conservancy's free Boojada Adventure educational walk at Gateway Trailhead, 18333 N. Thompson Peak Pkwy., 8 to 10 a.m.
- Nov. 1 to 30: DC Ranch Gives collects new, unwrapped toys, books and gifts at Desert Camp and The Homestead for Arizona's Children Association's Gifts of Hope program.
- Monday, Nov. 2: Bridge construction begins, weekdays 7 a.m. to 5 p.m.
- Tuesday, Nov. 3 and Wednesday, Nov. 4: The Ranch Association Board meets at 5 p.m. and the Community Council Board at 5:30 p.m., at Desert Camp or on Zoom. The 2027 budgets come up for approval at these meetings.
DC Ranch notes that event details are subject to change, and registration runs through Club Automation. For more on the neighborhood around the bridge, our DC Ranch community page and our look at Market Street's changing dinner rotation cover the blocks on either side of it.
Projects like this one tend to come up later, when a buyer drives the parkway or a seller gets asked what the construction near Desert Camp is. If you'd like to talk through how the finished crossing and the rest of the Thompson Peak corridor fit into a move you're considering, the team at Arizona Luxury Real Estate is happy to walk the route with you. Contact Us.